21 May 1998 marked the new beginning for Indonesia, known as
The Reformation, following the resignation of President Soeharto after ruling
the country for 32 years. Since then, Indonesia has embarked on a
decentralization program that shifts the central to sub-national
decision-making functions. However, 20 years later, Indonesia still experiences
inconsistency in managing this democratic approach, especially involving the
public. Firstly, the long period of centralization during the Soeharto's era
has left and ignored the local governments to equip the capacity to plan and
produce public goods (Nasution,
2016). Secondly, the local authorities
tend to shape the region based on their perceptions and interest, which exploit
the resources unsustainable to maximize the local income, ignoring the citizens'
social economy and political condition (Firman,
2010).
This essay will capture the phenomenon above in the form of the
community engagement process in the recent project of New Yogyakarta International
Airport (NYIA), located in the south-western part of Yogyakarta Province or
known as Yogyakarta Special Region (DIY). One of the main concerns in this
project is how the land clearing procedure was conducted. The different
interests of each landlord led to conflicts as the land was a job provider for
some farming tenants. The opposition to the project was considered vital as it
took six years, 2012 to 2018, to finish this land clearing procedure.
The essay will start with the basic concept of conflict. It
will then explore the case study context, followed by how the project of NYIA
conducted its public participation in the land clearing procedure. The essay
will also assess this agrarian conflict through the stakeholders' perspectives,
community engagement type, and power relations. Furthermore, there will be a
conclusion or lesson learned about why engaging local communities is essential
in every planning process.
Planning, governance,
and community engagement
Conflict is inevitable in life as humans need to interact
with others to fulfil their needs. As long as every person has different
interests and perspectives,ssdecision-making process of city planning, conflict
often occurs among the actors. It is a part of governance processes to
intervene the nature andspecificticgovernance process
Planning is defined as the process of governance to intervene
the nature and to achieve certain goals of urban outcomes (UN-Habitat,
2009), in which the governance is the
management of collective affairs gathered from formal government agencies and
other actors, including businesses and citizens (Healey,
1997a). A ' tDuring these complex processes
to decide what to do, ideally there are interactions and discussions between
actors such as government bodies, organizations, communities, and even
individuals (Queensland
Government, 2017). alignsaHowever, the process to
define one agreement sometimes meets a dead end which refers to the definition
of conflict, a perception that others have different value and interest (Pruitt,
2007).
sblockage regulations such as land use and ownership(Healey, 1997b)Consistent with Firman (2010) study, tthe personal interest of the local leaders. Furthermore, the concept of 'the king can do no wrong' in governance that inherits the old system of feudalism (Suhartono, 1999) might exacerbate the adverse impact of neoliberalism. Another impact that should be underlined is that the development might ignore the needs of the directly impacted communities and force them to be marginalized and deprived (Marcuse, 2009).
New Yogyakarta International Airport and its surroundings
DIY differs from the others as it has been awarded as a special region due to the historical context in helping Indonesia defend its independence against the Dutch. Based on the Special Laws (UUK)[1], the leader of this region will always be the Sultan and his descendants that hold the position of a governor. DIY consists of five city/regency: Yogyakarta city, Sleman, Bantul, Gunung Kidul, and Kulon Progo (Figure 1). These regions are widely known as the cheapest City in Indonesia due to their small minimum wages and cheap living costs. However, this remarkable region also has a high gap in economic distribution as most of the gross domestic product came only from Sleman, Yogyakarta city, and Bantul (Edita, 2019). Therefore, the NYIA is placed in Kulon Progo to overcome this economic gap (Regional Secretary of DIY, 2017).
Figure 1 The administration area of
DIY (adapted
from Dikpora, 2022)
NYIA was one of the top master plan projects (MP3EI)[2]
for accelerating and expanding Indonesia's economic development that aims to
attract investment, increase connectivity, and enhance the tourism industry of DIY
as the second most popular destination after Bali (Coordinating
Ministry for Economic Affairs, 2011). Furthermore, another reason behind
the project was that the previous airport (Adisucipto) originally belonged to
the National Army and could not be expanded to accommodate the increasing
projected tourists in the upcoming years and limited surrounding land (Angkasa
Pura, 2017). The new airport plan will have a
capacity of 14 million passengers per year and 35 aeroplane parks. Currently,
the new airport has been built and operated normally after six years of land
conflicts inside the planned-650-hectare land airport in the village of
Palihan, Sindutan, Glagah, Jangkaran, and Kebonrejo.
Stakeholders
involved
In the process of the NYIA governance, there are some
involvements of the stakeholders who have interests and influences (Table 1).
Stakeholders can be defined as a person or group of people interested in or
being affected by the ongoing issues (Glenorchy
City Council, 2017). The involved actors in NYIA
development are divided into three categories: the government, private, and
public.
In implementing MP3EI, improving regulations and permits at
the regional and national levels is key to success. The project of NYIA is the
responsibility of the Ministry of Transportation, and the local governments and
agencies must support it. Therefore, the government's players are the ones who
hold the critical paperwork in this project. It is similar to Roitman
(2016) study as the government has the most
substantial role in implementing policies and programs.
The project of NYIA also does not rely on the government but
also on an international investor. An international investor, GVK (an Indian
conglomerate), signed the MoU to deliver a funding injection to build the
airport with Indonesia's state-owned business in the related sector, Angkasa
Pura. According to Healey
(1997a), both actors will be considered the
private stakeholders because they are engaged in providing substantial subsidies
for the development.
Lastly, the public stakeholders are defined as a wide range
of actors from international and/or local NGOs to the grassroots level of the community
(Roitman,
2016). During the implementation of NYIA,
some groups formed, such as the opposers and the supporter of the proposed
development. Furthermore, there was also a legal aid institution similar to
NGO, which provides legal assistance.
Table 1 The identified stakeholders in
the NYIA development
|
Sector |
Stakeholder |
Role and interest |
|
Government |
Ministry
of Transportation |
The
actor has the responsibility to decide the final location of the airport. The
Ministry Regulation Number 836 on 2014 commands the local government to
adjust and update the land use regulation (Coordinating
Ministry for Economic Affairs, 2011; Sopanuddin, 2016). |
|
Provincial
Government of DIY, Governor or Sultan |
The Governor of
DIY is the one who has the right to issue The Land Use Permit (IPL). On the other
hand, as a Sultan, he also would like to declare and maximize the Sultanate
Ground[3]
as the new airport (Kurniadi, 2020;
Sopanuddin, 2016). |
|
|
Municipal
Government of Kulon Progo |
This
government stakeholder has the responsibility to design the land use and
together with the higher government to form an appraisal team to measure the
land (Marsudi et al.,
2019; Sopanuddin, 2016) |
|
|
District
Government of Temon and Village Leaders |
This government
facilitate the meeting between the higher government and the public. It also
delivers the message and announcement to the public (Marsudi et al.,
2019). |
|
|
Private |
Angkasa
Pura |
It
is a state-owned company that aims to govern and plan every airport in
Indonesia. Together with Provincial Government, Angkasa Pura also has
responsibilities to design, evaluate, and conduct public participation (Azizah, 2018;
Marsudi et al., 2019). |
|
GVK |
An Indian investor
plans to fund $500 million to the development of NYIA (Marsudi et al.,
2019). |
|
|
Public |
Wahana
Tri Tunggal (WTT), PWPP-KP[4] |
A
group of people (mostly consist of farmers from five affected villages) that
opposed to the NYIA project. Later on, as some of the members chose to change
side, they formed a new community, PWPP-KP in 2017 (Marsudi et al.,
2019; Sopanuddin, 2016). |
|
LBH Yogyakarta |
An institution
that had interest to help WTT to assess and watch the development of NYIA
from the law legal perspective (Sopanuddin, 2016). |
|
|
The
supporters |
The
locals who support the NYIA with some conditions (Sopanuddin, 2016). |
Type of community engagement
2012 to early 2014
According to Sopanuddin
(2016), the local citizens started to feel
insecure in 2012 as the issue of building a new airport had been growing more
pronounced in the mass media. Of 11,000 citizens of five villages, 8,400 people
opposed the airport (Marsudi
et al., 2019). Furthermore, most people rejected
the airport issue because they feared losing jobs and lands as farmers. Therefore,
some of them decided to form a community, namely Wahana Tri Tunggal (WTT)
(Marsudi
et al., 2019). On 12 Sept 2012, some
local stakeholders met the Bupati[5]
Kulon Progo to verify the issue, but there was no clear answer. The Sultan also
did not want to pronounce the final location of the airport to avoid an extreme
increase in the land price, which might exacerbate the land clearing procedure (Marsudi
et al., 2019). As the unclear issue became a hot
topic and sensitive, WTT asked for assistance from LBH Yogyakarta and attached
rejection banners along the Daendels National Street.
In 2013, there were some published reports on a feasibility
study in the coastal area of Kulon Progo by local universities and
institutions. A study by Marsudi
et al. (2019) shows that these activities gave hope
to the locals that the airport development might be canceled. However, the
study also noted that an airport appraisal team from Angkasa Pura, accompanied
by the local government, suddenly conducted a land measurement and benchmarks
in January 2014 without prior notice. The arrival of that team triggered the
anger of the WTT, which led to a massive blockade on Daendels Street and
demonstrations in the village council buildings. On the other hand, Marsudi
et al. (2019) also noted that the village leader
gave no comment and responded that the benchmarking was the order from the
provincial government.
2014 – 2019
Nine months later, the government of Yogyakarta announced the
final development proposal of a new international airport that would be built
in Temon, Kulon Progo. According to Azizah
(2018), that process is a part of informing
through mass media and press conferences. Figure 2 illustrates the timeline
plan to conduct the community engagement by the Government of Yogyakarta
accompanied by the lower governments. The early screening was formal
presentations and field trips from the government to each affected village
council building. This stage was followed by the public consultations in which,
among 2546 invited citizens, there were 396 who did not attend (Marsudi
et al., 2019). The first consultation aimed to
capture all the citizens' perspectives and feedback toward the airport project,
while the second one presented the government's responses to critiques and
comments from the first consultation (Azizah,
2018). During those events, the private
and government agreed to fulfill the people's requests: high land compensation,
relocation houses, and airport jobs provision (Edita,
2019; Marsudi et al., 2019; Sopanuddin, 2016).
Figure 2 The timeline plan for public
participation in NYIA (Azizah,
2018)
During the building process of NYIA, Angkasa Pura and the
local government held 15 training programs for corporate social responsibility
(CSR). Table 2 shows that the programs were held from 11 July 2018 to 25 May
2019, dominated by General English training classes. However, Az-Zahra
and Sigit (2019) survey depicts that most former
farmers still experience hard times adapting and looking for airport jobs. Some
of them complained that the relocation houses provided by the private
stakeholders are tiny and do not support cattle farming activity. Furthermore,
the compensation money was hugely reduced as most of them failed to try a new
business or rent farming land due to unclear job provisions from the airport
for the locals.
Table 2 The training classes provided
by the private for the empowerment of the locals (Susanto,
2020)
|
Events |
Total number of participants, receipts |
Time range |
|
4x
General English class |
40/session |
11 Jul – 7 Dec 2018 |
|
How
to fix air conditioner |
|
8 Oct –
10 Nov 2018 |
|
Welding
class |
|
10 Dec 2018 – 11 Jan 2019 |
|
Electricity
class |
|
|
|
Stone
and wood crafting class |
|
12 Nov – 17 Dec 2018 |
|
Financial
aids for students |
238 |
6 – 24
Aug 2018 |
|
PAUD
teaching class |
17 |
10 – 31 August 2018 |
|
Disability
empowerment class |
|
15 Aug –
12 Oct 2018 |
|
Elders
empowerment class |
|
15 Aug – 12 Oct 2018 |
|
Cattle
farming class |
|
1 Oct –
14 Dec 2018 |
|
Agribusiness
development class |
|
1 Oct – 30 Nov 2018 |
|
Fishermen
empowerment class |
|
3 Sept –
31 Oct 2018 |
|
Entrepreneurship
class |
|
2 Jan – 29 Mar 2019 |
|
Tourism
industry class |
|
5 Mar –
27 Apr 2019 |
|
Airport
supporting system class |
|
12 Mar – 25 May 2019 |
Blank spaces = no data
Based on these findings, the public participation conducted
by the government and the private is 'consult'. It is a method that acknowledges
the public perspectives to provide alternative decisions (IAP2,
2014). The government listened and agreed
to deliver the public requests (compensation, relocation, and job provision).
However, this participation couldn't be defined as 'involve' as there was still
no effort from the private and government to ensure that the aspirations were
well reflected in the final decision (Figure 3).
Figure 3 The public participation
spectrum (IAP2,
2014)
Power relations
Elite perspectives
In the UUK, it is stated that the Government of DIY, led by
the Governor (Sultan), can decide whatever regulations that support the culture
preservation. For example, the Sultan's servant can be defined as someone
identified as a government officer, including local leaders and the military[6].
As administration leaders in DIY are considered Sultan's servants, they have
the right to use the Sultanate Ground as a gift for their loyalty[7].
In the case of NYIA, the village government only acted as announcers from the
higher-level government (province and municipality) instead of giving responses
to the mass demonstration in September 2014 or representing the opposition
perspectives back to the higher hierarchy (Marsudi
et al., 2019; Sopanuddin, 2016). Furthermore, there was an
indication of media control as Arifin
and Basuki (2018) found that the local news only
emphasized the positive impacts of NYIA without covering the essential
opposition's views such as land deprivation and farmers criminalization. According
to Ife
(2016), such events show the true control
of key institutions from certain elite groups as a 'power over' to dominate the
least powerful entity.
On the other hand, these elites were also able to perpetuate
the project behind the public scene as Susanto
(2020) found that the final decision on the
airport was made in early 2014. However, the locals started late to know the
formal announcement was delivered in September 2014. This decision made by the
Ministry of Transport and the Provincial government can be considered a 'hidden
power' due to the exclusion of other less powerful groups (Gaventa,
2006).
In 2016, the hot issue of NYIA became so sensitive as the WTT
experienced the 'power over' from the police and surrounding neighbors (Marsudi
et al., 2019; Sopanuddin, 2016). The police and the appraisal team
from Angkasa Pura, and PLN[8]
officers insisted on measuring the remaining land and cutting the electricity.
Heavy equipment such as bulldozers also existed to clear the farming crops. Both
sides' anger peaked as crying, beating, and changed words worsened the day.
Such a thing had entered a new stage of the conflict, escalation, described as
angry statements and heavy contentious tactics posing dangerous threats to a
conflict (Table 3) (Pruitt,
2007).
Table 3 The
different perspectives that caused a conflict escalation
|
Stakeholders |
What they think |
|
WTT |
The members wanted to stay as farmers. They believe that their
farming lands have always belonged to them since their grandparents held the
land ownership certification. They never agreed on Rijkblad[9]
and the consignment process (Marsudi et al.,
2019). |
|
Angkasa Pura, PLN, and Police |
Following the consignment[10]
decision from the Governor, these stakeholders believed that the WTT must
take the compensation money through the consignment process to process the
development soon (Marsudi et al.,
2019). |
|
Surrounding neighbors |
As they supported the NYIA, the neighbors helped with the land
clearing procedure (Sopanuddin, 2016). |
Market centrality
According to the land-use plan of Kulon Progo, the land in
Temon was mainly planned to stay as an agricultural area. This plan was
supported by the massive production of crops from the affected villages (Figure
4). Those conditions, including the proof of land ownership, were why the
attorney picked the WTT as the winning side and canceled the IPL on 23 June
2015 (Sopanuddin,
2016). However, as this decision was
revoked by the Supreme Court a week later, the NYIA stood still. Such acts indicate
market centrality with the neoliberalism principle as the airport development
is outside the trajectory plan of the local authority (Minnery,
2007), which led to a reducing the
blockade through changing the land use plan (Healey,
1997b).
Figure 4 The total production of
farming crops in five affected villages (Indonesian
Statistics, 2015 adapted from Pratama & Yahsyi, 2016)
Effort to empower
To balance the elite power, Ife
(2016) emphasizes empowerment by allying
with other powerful elite. The WTT sought legal assistance from LBH Yogyakarta.
This community felt that they never were invited to join the public
participation as they rejected the proposal (Edita,
2019). With this new partnership, WTT analyzed
the problem and formed strong arguments for collective action delivered in streets,
council buildings, and courts (Figure 5). It was successful as it canceled the
IPL. This synergy among both actors is considered 'power with' as they acted
together in solidarity (Ife,
2016).
Figure 5 a) A well-known poster during the conflict time, b) the community was discussing a strategy, and c) a mosque was converted to be the main gathering post, the banner said "mosque is for praying, not for an airport!"
Formed communities
A community is a group of people who identify themselves due to
their similarities or having something in common (Gallent
& Ciaffi, 2014). There are two types of
community: community-based on location and community-based on identity. A community
based on location or socio-spatial community is a group of people due to their
close residential proximity. In the case of NYIA, the people who opposed the
project formed a community, namely Wahana Tri Tunggal (WTT) (Sopanuddin,
2016). The community members were primarily
farmers (the landlord and farm cultivators[11]) from
Palihan and Glagah, as NYIA affected more land and people in both villages.
There is also a small number of people from the rest of the three villages.
Therefore, WTT can be considered a socio-spatial community. Typically, this
community is only an accident of residency that lacks deeper motivation, and
the bond is not strong (Bell
& Newby, 1976; Delanty, 2003 from Gallent & Ciaffi, 2014).
However, WTT had a strong bond considering that they ever had a thriving
social action. With the help of Legal Aid Institute Yogyakarta (LBH)[12]
and massive protests, the community won the court on 23 Jun 2015.
The Location Permit (IPL)[13]
issued by the Governor was revoked. This collaboration of WTT and LBH
Yogyakarta to protest, raise the aspirations, and win the court is the reactive
action toward the NYIA development. Those reactive activities are one of the
community action drivers characterized by protest and lobbying as the initial
response (Gallent
& Ciaffi, 2014).
On the other hand, these involved communities' thinking has evolved using the internet and social media. The winning story was heard across the country and inspired the other communities through Kamisan[14]. For example, the Kamisan in Bandung[15] brought the winning story of WTT to inspire the slum community of Tamansari to fight against the housing development which would take their land. They posted about their own story, but they also shared the struggle of the other communities experiencing the same issues (Figure 6). They did so to raise their issues and show support one to another. Such activities prove that people could find a stronger connection with clear goals through online platforms rather than offline, although it diminishes the spatial fixity (Gallent & Ciaffi, 2014).
Figure 6 a) Through a social media
account, the NYIA opposers showed support for Tamansari, Bandung, and b) vice
versa
The essential rationale for a better community engagement
Empowerment
Empowerment is defined as acts to increase the power of the
less-fortunate community (Ife,
2016). As the farming land would be
converted to concrete, the farmers would be disadvantaged as that process would
disrupt their social capital. Farming is not merely a plant-harvest cycle but a
hereditary job from generation to generation which connects people to people in
the form of gotong royong[16]
to create collective welfare (Sopanuddin,
2016; Szreter & Woolcock, 2004). It is considered normal to question
the airport proposal that would take their social capital. In the case of NYIA,
the locals did not aim to gain more power, but they wanted to be empowered with
information about the airport. Based on Martin
(2007), those methods are considered social
activism as the citizens had no power or significant influence to challenge the
decisions. Furthermore, he also notes that the characteristic of
future-oriented activism is seeking changing relationships as the exclamation
point, such as greater equality and worker participation in the decision
process. The public participation of NYIA met this characteristic as, finally,
they looked forward and demanded job provisions in the airport (Sopanuddin,
2016).
Transparency
In order to achieve an inclusive city in 2030, community
engagement is an essential tool as it provides a common understanding between
actors that brings accountability and transparency. Although hundreds of people
initially opposed NYIA, the conducted public participation successfully reduced
the number of opposers to approximately 30 people in 2017 (Marsudi
et al., 2019). This act was because the actors
started to understand one another perspectives through negotiation. Therefore, it
is essential to provide transparency and conduct public participation as early
as possible to minimize the conflict between actors.
Social justice and inclusivity
WTT experienced a shrinking number of the members due to
changing sides in 2016 – 2017 due to criminalization[17]
and intimidation (forced house demolishment, electricity cut, and polluted
wells by their neighbours) in the name of nationalism[18]
(Marsudi
et al., 2019). Most of the remaining members who
formed a new community, namely PWPP-KP were considered land cultivators by the
Governor[19].
In the feudal system, these people are called kawula or the lowest level
in social status (Suhartono,
1999). Furthermore, they can also be
considered victims of how The Sultan took over a land-based on historical and
informal relations (Kurniadi,
2020). Even after the finish of the airport
project, most of the public who live in relocation houses still cannot adapt to
the changes (Az-Zahra
& Sigit, 2019). Those conditions are defined by Marcuse
(2009) as the deprived, which the
definition is as follows,
'… those who directly oppressed, the homeless, the hungry,
the imprisoned, the persecuted on gender, religious, and racial grounds… those
superficially integrated into the system and sharing in its material benefits,
but constrained in their opportunities for creative activity, oppressed in
their relationship… unfulfilled in their lives' hopes.'
In every project development, an
initiative must come initially from the grassroots community that understands
the demand and surrounding conditions (Wakely,
2020). Therefore, a good community
engagement will deliver both traits in 'collaborate' and 'empower' ways as it
triggers the deprived community to formulate solutions or implement policies (IAP2,
2014).
Conclusion
The NYIA project is one of the grand plans of Indonesia in
Kulon Progo, DIY, to maximize economic investment. The engagement process of the project focused
on the land clearing procedure that was considered slow and complex, and it
took six years with a lot of tensions and conflicts. While the opposition
formed a community, namely WTT and kept rejecting the project by having social
movement and blocking the road, the public supporters demanded some requests
such as high compensation, relocation houses, and job provisions. This study
finds that each stakeholder has a different perspective and unequal power
distribution. Although the government took aspirations, the spectrum of public
participation was still considered 'inform' because the government and private
did not ensure to fulfil the received feedback.
Based on how the NYIA conducted its community involvement, we
can conclude that it lacked community empowerment, late transparency, and lack
of inclusiveness, especially from the disadvantaged group. Therefore, community
engagement is a critical element in planning because it empowers the people. In
NYIA, lack of empowerment led to a massive social protest of the WTT, which
other communities had empowered against the development. Secondly, it creates
mistrust or trust in the government. The study showed that late undetailed
transparency triggered the people to request a high land compensation. Lastly, it
is an opportunity to enforce inclusivity and social justice. Learning from
NYIA, excluding the deprived led to an unsustainable community as they will be
marginalized from the airport due to their improvisational skills.
References
Angkasa Pura.
(2017). Catatan CEO [CEO's Note]. Babat
Alas Nawung Kridha, Babak Baru Bandara Yogyakarta [The New Stage of Yogyakarta
Airport], 9. https://ap1.co.id/contents/file/439-ANGKASA_PURA_MAGAZINE_EDISI_JANUARI-FEBRUARI_2017.pdf
Arifin, K. A., & Basuki, U. (2018). Media dan NYIA: Analisis
Wacana Kritis Pembangunan Bandara Baru Yogyakarta dalam Media Lokal [Media and
NYIA: Critical Analysis on NYIA from the Perspective of Local Mass Media]. Jurnal Komunikasi, 13(1), 69-80. https://doi.org/10.20885/komunikasi.vol13.iss1.art5
Az-Zahra, Y. F., & Sigit, A. A. (2019). Analisis Dampak Sosial
Ekonomi Pembangunan Bandara New Yogyakarta International Airport terhadap
Kehidupan Masyarakat di Kecamatan Temon, Kabupaten Kulonprogo, Daerah Istimewa
Yogyakarta [Socio-Economic Impacts of NYIA for the Livelihood of Temon, Kulon
Progo, DIY]. Undergraduate Theses,
Faculty of Geography, Universitas Muhammadiyah Surakarta. http://eprints.ums.ac.id/73280/
Azizah, N. (2018). Dampak Sosial Ekonomi Pembebasan Lahan
Pembangunan Bandar Udara Yogyakarta [The Socio Economic Impact of the Land
Clearing Procedure of Yogyakarta International Airport]. Politika Jurnal Ilmu Politik,
8(2), 76-91. https://doi.org/10.14710/politika.8.2.2017.76-91
Coordinating Ministry for Economic Affairs. (2011). Masterplan Acceleration and Expansion of
Indonesia Economic Development 2011-2025. Ministry of National Development
Planning/National Development Agency. https://www.aseanbriefing.com/userfiles/resources-pdfs/Indonesia/FDI/ASEAN_Indonesia_Master%20Plan%20Acceleration%20and%20Expansion%20of%20Indonesia%20Economic%20Development%202011-2025.pdf
Dikpora. (2022). Data Satuan
Pendidikan DIY [The Data of Educational Institutions]. Dinas Pendidikan
Pemuda dan Olahraga. Retrieved 5 June 2022 from https://dikpora.jogjaprov.go.id/web/
Edita, E. P. (2019). Aerotropolis: At What Cost, to Whom? Master Thesis Series in Environmental
Studies and Sustainability Science, Lund University, 32. https://lup.lub.lu.se/student-papers/search/publication/8980037
Firman, T. (2010). Multi local-government under Indonesia's
decentralization reform: The case of Kartamantul (The Greater Yogyakarta). Habitat International, 34(4), 400-405. https://doi.org/https://doi.org/10.1016/j.habitatint.2009.11.005
Gallent, N., & Ciaffi, D. (2014). Community action and planning.
In N. Gallent & D. Ciaffi (Eds.), Community
action and planning: Contexts, drivers and outcomes (1 ed., pp. 1-16).
Bristol University Press,. https://doi.org/10.1332/policypress/9781447315162.003.0001
Gaventa, J. (2006). Finding the Spaces for Change: A Power Analysis.
IDS Bulletin, 37, 23-33. https://doi.org/10.1111/j.1759-5436.2006.tb00320.x
Glenorchy City Council. (2017). Community
Engagement Procedure. Community Planning and Inclusion Glenorchy City.
Healey, P. (1997a). Planning and Governance. In P. Healey (Ed.), Collaborative Planning: Shaping Places in
Fragmented Societies (pp. 205-242). Macmillan Education UK. https://doi.org/10.1007/978-1-349-25538-2_7
Healey, P. (1997b). Traditions of Planning Thought. In P. Healey
(Ed.), Collaborative Planning: Shaping
Places in Fragmented Societies (pp. 7-30). Macmillan Education UK. https://doi.org/10.1007/978-1-349-25538-2_1
IAP2. (2014). Public
Participation Spectrum. International Association for Public Participation
Federation. https://iap2.org.au/wp-content/uploads/2019/07/IAP2_Public_Participation_Spectrum.pdf
Ife, J. (2016). Chapter 3 Foundation of community development:
ecological and social justice perspectives. In Community Development in an Uncertain World: Vision, Analysis and
Practice (2 ed., pp. 44-73). Cambridge University Press. https://doi.org/10.1017/CBO9781316342855
Kurniadi, B. D. (2020). Defending the Sultan's Land: Yogyakarta,
Control over Land and Aristocratic Power in Post Autocratic Indonesia. Open Access Theses, The Australian National
Univeristy. https://doi.org/10.25911/5e3a934e0d160
Marcuse, P. (2009). From critical urban theory to the right to the
city, City: analysis of urban trends, culture, theory, policy, action. City,
13(2-3), 185-197. https://doi.org/10.1080/13604810902982177
Marsudi, Rosalina, K. E., & Sunarso. (2019). Resolusi Konflik
Agraria Pada Pembangunan New Yogyakarta International Airport (NYIA) dalam
Perspektif Hak dan Kewajiban Negara [Agrarian Conflict Resolution on NYIA from
the Perspective of Citizen's Right and Obligation]. Master Theses, Faculty of Social Science, Universitas Negeri Yogyakarta.
https://eprints.uny.ac.id/66284/
Martin, B. (2007). Activism,
Social and Political. Encyclopedia of Activism and Social Justice. https://www.bmartin.cc/pubs/07Anderson.pdf
Minnery, J. (2007). Stars and their Supporting Cast: State, Market
and Community as Actors in Urban Governance. Urban Policy and Research, 25(3),
325-345. https://doi.org/10.1080/08111140701540745
Nasution, A. (2016). Government Decentralization Program in
Indonesia. ADBI Working Paper, 601. https://www.adb.org/sites/default/files/publication/201116/adbi-wp601.pdf
Paryanto. (2016). Dinamika Politik Keistimewaan di Daerah Istimewa
Yogyakarta Pasca UU Nomor 13 Tahun 2012 [The Political Dynamics of DIY on the
Regulation Number 13 of 2012]. Master
Theses, Faculty of Social Science, Universitas Muhammadiyah Yogyakarta. http://repository.umy.ac.id/bitstream/handle/123456789/8823/Tesis%20Paryanto%20-%20Politik%20Keistimewaan%20DIY%20-LENGKAP%20%281%29.pdf?sequence=1&isAllowed=y
Pratama, A. B., & Yahsyi, A. (2016). Para Penantang Sultan dari Kulon Progo [The Sultan Opposers from Kulon
Progo]. CNN Indonesia. https://www.cnnindonesia.com/nasional/20160830195456-20-154975/para-penantang-sultan-dari-kulon-progo
Pruitt, D. G. (2007). Social Conflict: Some Basic Principles. Journal of Dispute Resolution, 1(8). https://scholarship.law.missouri.edu/jdr/vol2007/iss1/8
Queensland Government. (2017). Community
engagement toolkit for planning. Department of Infrastructure Local Government
and Planning.
Regional Secretary of DIY. (2017). Forum Tematik: Bandara Baru, Mewujudkan DIY sebagai Daerah Tujuan
Wisata dan Budaya Kelas Dunia [Thematic Forum: NYIA, Achieving DIY as
World-Class Tourist and Culture Destination]. Asisten Perekonomian dan
Pembangunan Setda DIY. http://bappeda.jogjaprov.go.id/download/download/379
Roitman, S. (2016). Top-Down and Bottom-Up Strategies for Housing
and Poverty Alleviation in Indonesia: The PNPM Programme in Yogyakarta. In S.
Attia (Ed.), Dynamics and Resilience of
Informal Areas (pp. 188-210). Springer International Publishing Switzerland.
https://doi.org/10.1007/978-3-319-29948-8_11
Sopanuddin, A. (2016). Konflik Lahan Pertanian dalam Pembangunan
Bandara International di Kulon Progo [Farming Land Conflict inside the Project of
International Airport in Kulon Progo]. Undergraduate
Theses, Faculty of Social Science, Universitas Negeri Yogyakarta. https://eprints.uny.ac.id/41367/
Suhartono. (1999). Feudal Heritage: Source of Corruption, Collusion,
and Nepotism. Humaniora, 11, 15-20. https://doi.org/10.22146/jh.672
Susanto, H. (2020). Analisis Dampak Sosial Ekonomi dalam Pembangunan
Yogyakarta International Airport di Kulon Progo [Socio-Economic Impacts of
NYIA, Kulon Progo]. Majalah Ilmiah Bijak, 17(1). https://ojs.stiami.ac.id/index.php/bijak/article/download/820/460
Szreter, S., & Woolcock, M. (2004). Health by association?
Social capital, social theory, and the political economy of public health. International Journal of Epidemiology, 33(4), 650-667. https://doi.org/10.1093/ije/dyh013
UN-Habitat. (2009). Planning
Sustainable Cities, Global Report on Human Settlements. Earthscan. https://unhabitat.org/sites/default/files/download-manager-files/Global%20Report%20on%20Human%20Settlements%202009%20Planning%20Sustainable%20Cities.pdf
Wakely, P. (2020). Partnership: a strategic paradigm for the
production & management of affordable housing & sustainable urban
development. International Journal of
Urban Sustainable Development, 12(1),
119-125. https://doi.org/10.1080/19463138.2019.1647016
[1] Special Laws is Regulation Number 13 of 2012 known as Undang
Undang Keistimewaan (UUK).
[2] Master Percepatan dan Perluasan Pembangunan Ekonomi
Indonesia (MP3EI).
[3] Sultanate Ground is defined as land which belongs to
the Sultan.
[4] Paguyuban Warga Penolak Penggusuran Bandara Kulon
Progo (PWPP-KP).
[5] The Lordman or leader of municipality.
[6] The Sultan’s servant is divided into two groups. One
of them is Keprajan, the Sultan’s servant from government bodies.
Through the UUK, Paryanto (2016) indicates a conflict of interest.
[7] Not only receiving monthly salary, a local leader
affiliated with Sultan will received a land called as bengkok. This land
should be returned after finishing the job.
[8] Perusahaan Listrik Negara (PLN) is a
state-owned company that has a responsibly on house electrification.
[9] It is an old regulation that states ‘every land
that has no ownership proof belongs to the king’.
[10] It is a mechanism where the money of land compensation
for the opposed is entrusted to the court.
[11] It is also known as buruh tani and kawula,
a farmer who has no land ownership and farm for the land owner.
[12] Lembaga Bantuan Hukum (LBH).
[13] Izin Penetapan Lokasi (IPL).
[14] Kamis means Thursday. It is a human and land
right activism which exist in almost every city in Indonesia. This event was
initially to ask the government every Thursday to look for the missing people,
inspired by the mothers of Plaza de Mayo, Argentina.
[15] It is the capital city of West Java Province, more
than 300 km from DIY.
[16] Generally, it is a culture of the citizens of DIY to
help other people in a collective (together) way such as planting, harvesting,
and selling the rice.
[17] Due to the social protest in September 2014, some of
the farmers were jailed (Sopanuddin, 2016).
[18] The development of NYIA is based on Regulation Number
2 of 2012, the land clearing is for the national importance (Azizah, 2018).
[19] These land cultivators have no land ownerships. They
fear the NYIA will take the farmland as their main job provisions. Furthermore,
they will only get a little compensation in the consignment process (Marsudi et
al., 2019).